The purpose of the project is to provide technical assistance and supervision for the construction of the North Nicosia Sewerage System, which consists of approximately 13 km of sewer and four Pump Stations in the pre-construction, construction, and post-construction phases. The main parts of the sewer will be built in river beds, and the use of no-dig techniques is planned to cross several bridges. Additionally, the project includes the rehabilitation of the Pedieos/Kanlıdere River and its surroundings to ensure safety. The Pedieos/Kanlıdere River Rehabilitation project involves the design and construction of a bicycle path along the river based on geographical and topographical studies. Within the scope of this project, technical assistance and supervision services are required to ensure that the wastewater infrastructure works funded by the European Union are designed, constructed, and commissioned in accordance with the relevant technical specifications and requirements without any delays or cost overruns until the project is completed. All activities during pre-construction, construction, and post-construction phases, including the reports provided, commissioning, and testing procedures, will be monitored and supervised until the project is completed.

Definition of the actual services provided by our personnel within the scope of the task:


  1. Supervising the construction of the Project implemented under the FIDIC “Red Book” conditions:

  • Pre-Award Activities and Ceremony

  • Monitoring During the Construction Phase

  • Control and approval of quality assurance procedures,

  • Approval of the contractor's preliminary presentations, review of insurance policies,

  • Approval of the Contractor’s Preliminary Design Report

  • Approval of the Contractor’s Detailed Design Report

  • Approval of all hydraulic models used to assess constructions in the riverbeds

  • Approval of the Preliminary and Final Project Reports of the Pedieos/Kanlıdere River Rehabilitation Project

  • Examination and approval of the contractor's compliance with technical specifications


  1. Information Management and Reporting:

  • Preparation of the field supervision guide,

  • Preparation of the financial control procedures manual,

  • Preparation of the quality assurance file and guide,

  • Preparation of completion reports,

  • Providing technical support during the tender, contract, and execution phases of the project

  • Assisting the client during the evaluation of proposals,

  • Assisting the client during negotiation procedures,

  • Reviewing the design of the works before implementation,

  • Providing a second opinion based on technical specifications,


  1. Supervision of Correcting Deficiencies

  2. Witnessing Tests After Completion

  3. Certification Final Payment Works Contract

  4. Additional activities/extensions of works


io Environmental Solutions Research and Development Ltd.

Contact

Istanbul

Ankara

Reşitpaşa Mah. Katar Cad. Arı Teknokent 1 2/5 D: 12 34469 Sarıyer

Phone: 0 (212) 276 65 48
Fax: 0 (212) 276 33 67
E-mail: info@iocevre.com

Copyright ©

2024

io Environmental Solutions Research and Development Ltd.

io Environmental Solutions Research and Development Ltd.

Contact

Istanbul

Ankara

Reşitpaşa Mah. Katar Cad. Arı Teknokent 1 2/5 D: 12 34469 Sarıyer

Phone: 0 (212) 276 65 48
Fax: 0 (212) 276 33 67
E-mail: info@iocevre.com

Copyright ©

2024

io Environmental Solutions Research and Development Ltd.